Champlain Hudson Power Express: Project Development Portal
Arrow
Project Update Sign-up

Project Schedule

TDI is committed to making the development of this project open and transparent for regulators and citizens alike. This page presents a summary of the major milestones achieved to date and the milestones that will be achieved between now and the onset of construction activity.

As is the case with any project of this magnitude, there are multiple levels of review at the state and federal levels, and the outline below is subject to change. Please check back periodically for updates. This page was last updated on January 20, 2016.

Winter 2009/2010
  • Presidential Permit application made to the U.S. Department of Energy (DOE) - Filed January 2010
  • Initial Article VII application made to New York State Public Service Commission (PSC) - Filed March 2010
Spring 2010
  • First public meetings held along the route - 5 public meetings completed by May 2010
Summer 2010
  • Marine Route Survey completed - July 2010
  • Federal review process begins - 7 public meetings completed by July 2010
  • Federal Energy Regulatory Commission authorizes the project to charge negotiated rates - Granted July 2010
  • Article VII application completeness determination - Issued August 2010
Fall 2010
  • Application made to the U.S. Army Corps of Engineers and the New York Department of State for federal permits and reviews, including "coastal zone consistency"
  • Article VII hearings commence - 5 public meetings completed by November 2010
  • Article VII settlement meetings commence
Winter 2010/2011
  • New York Independent System Operator approval of Project's System Reliability Impact Study - granted March 2011
Spring 2011 Summer 2011
  • 20 Members of NYS's Congressional delegation sign letter urging favorable action on the Project's application
Fall 2011
  • TDI advises PSC administrative law judges that settlement negotiations are making progress
Winter 2011/2012 Spring 2012 Summer 2012
  • PSC evidentiary hearings on Joint Proposal held July 18-20
  • Final briefs submitted in Article VII process on September 7th
Fall 2012
  • Second Marine Route Survey Completed – November 2012
Winter 2012/2013 Spring 2013 Summer 2013
  • New York Independent System Operator accepts Astoria-Rainey Cable as elective system upgrade facility.
Fall 2013 Winter 2013/14
  • Public comment period ends
  • Department of State Concurrence
Spring 2014
  • Programmatic Agreement Executed
Summer 2014 Fall 2014 Winter 2014/2015
  • TDI advises New York Independent System Operator (NYISO) that it will participate in its Class Year 2015 studies
Spring 2015 Summer 2015
  • NYISO hosts kick-off working group meeting for Class Year 2015
Fall 2015
  • Cultural Resources Management Plans submitted to DOE
Winter 2015/2016
  • Quebec Energy Minister Arcand endorses project
Spring 2016
  • Navigational Risk Assessment submitted to Army Corps